Integrated Operation Rules and Guidelines (IORG)
Document 2A – 2E: Utility Load Shedding
Objective
This document outlines the steps and action plans to be implemented during utility supply disruptions, detailing roles and responsibilities to ensure that PIC operations remain safe, smooth, and efficient.
Scope
This document is applicable only during abnormal situations where there is an interruption in the supply of utilities from producers to consumers, in order to prevent a total shutdown of the complex.
List of Utility
1. Steam.
2. Natural Gas
3. Electricity
4. Water (Treated Water), Demin Water and Boiler Feed Water)
5. Air (Instrument and Process)